Ongoing capital projects (per the City)
In progress (4)
- Varra Park Hillside Stabilization per the City's timeline: Data Gathering and Geotechnical Field Work: May - June2026Preliminary Design: July - October 2026 (Completed)Final Design: November - January 2027Construction: TBD The City's page
- 10th at Birch Intersection Improvements The 10th Avenue at Birch Street intersection improvements project aims to improve safety around the Birch Elementary School. per the City's timeline: Final Design: May - September 2026Utility Coordination and Relocation: July 2026 - April 2027Winter 2026: The budget, scope, prioritization and timing of the project are being re-evaluated due to the planned closure of Birch Elementary School. The City's page
- 112th & Uptown Avenue Street Improvements per the City's timeline: Preliminary Items: June 2025.Phase 1A & 1B Tasks - East End/North Side of W. 112th Ave: August thru October 2025Phase 2A & 2B -Outside ROW / North & South of W. 112th Avenue: October through May 2026Phase 3 - Misc. Closeout Tasks: May thru July 2026.Project Completion: Summer 2026 The City's page
- Airport Creek Trail Underpass per the City's timeline: Initial Alternatives Analysis: 2022 - completed.Federal grant Intergovernmental Agreement with CDOT: 2023 - completed.Federal grant: 2024 - completed.Preliminary design for the preferred alternative: 2024/2025Public outreach: 202560% design: May 2026 - completed.Fall 2026: The design is currently paused while the feasibility of an underpass at the planned 116th rail platform is evaluated. The budget, scope, prioritization and timing of the Airport Creek Trail Underpass will be re-evaluated if an underpass is included with the passenger rail station/platform at 116th Avenue. The City's page
Complete (1)
- Stoneybrook Drive Retaining Wall Replacement Complete ยท per City summaryThe Stoneybrook Drive Retaining Wall Replacement project is now complete. per the City's timeline: Construction Start: November 2025Construction Completion: April 2026. The City's page
Timeline: see the City's page (22)
- Broadlands West Park Retaining Wall Replacement per the City's timeline: Construction Quotes: End of August and Early September 2026Construction: Fall 2026 The City's page
- Broomfield Police Building Expansion The proposed building is approximately 83,000 SF, and is proposed to be located at the southeast corner of DesCombes Drive and 3rd Avenue. per the City's timeline: Construction is anticipated to start in Summer 2026 and take approximately 20 months to complete. Cost, per the City: The project is anticipated to cost $81.6M. The City's page
- Kohl St & Daphne St Multimodal Improvements The primary objective of this project is to improve pedestrian and bicycle safety along Kohl Street, specifically at the intersection of Daphne Street. per the City's timeline: December 2026: Installation of Rectangular Rapid Flashing Beacons (RRFBs) is anticipated as part of the construction work. The City's page
Developments and ordinances followed through council and commission meetings are on city hall projects.
About this page
Sources: City of Broomfield: Current Capital Improvement Projects
27 projects on the City's list of current capital improvement projects. Phases and dates are the City's own words. The groups above only sort them by the City's timeline lines; a project is Complete "per City summary" when the City's own summary says the whole project is complete and no timeline line is dated after today.
Last checked Nov 28, 2026.
We check it once a day. We read the City's list and each project's own page, and copy the timeline lines, the cost line and at most one short sentence exactly as written. When a line changes, the project's page here records the change with the date we saw it. If the City's page cannot be read, we keep the last version we read and its date. Schedules change: the City's page is the one to rely on.