In progress
Airport Creek Trail Underpass
Timeline, per the City's timeline
- Initial Alternatives Analysis: 2022 - completed.
- Federal grant Intergovernmental Agreement with CDOT: 2023 - completed.
- Federal grant: 2024 - completed.
- Preliminary design for the preferred alternative: 2024/2025
- Public outreach: 2025
- 60% design: May 2026 - completed.
- Fall 2026: The design is currently paused while the feasibility of an underpass at the planned 116th rail platform is evaluated. The budget, scope, prioritization and timing of the Airport Creek Trail Underpass will be re-evaluated if an underpass is included with the passenger rail station/platform at 116th Avenue.