112th & Uptown Avenue Street Improvements

Timeline, per the City's timeline

  • Preliminary Items: June 2025.
  • Phase 1A & 1B Tasks - East End/North Side of W. 112th Ave: August thru October 2025
  • Phase 2A & 2B -Outside ROW / North & South of W. 112th Avenue: October through May 2026
  • Phase 3 - Misc. Closeout Tasks: May thru July 2026.
  • Project Completion: Summer 2026

Changes we have seen

None yet. Each day we compare the City's page with the version we read before and list any change here with its date.